Buck Hill Addition & Basement Remodel
Click on photos to enlarge:
Flashings are sealed to windows
House is wrapped
Paper over upper Vycor
Vycor over metal window flashing
Vycor over paper and metal flashing
Upper paper over metal flashing
Vycor over paper,metal flashing over Vycor
Lower paper with metal flashing for bricks
Vycor flashing over brick ledge
10 mil poly covering over crawlspace floor
Crawlspace foundation walls are insulated with closed cell foam
Floor rim is foamed
Stapled netting for blown insulation over closed cell foam
Headers are foamed full
Walls are insulated with 2 inches, R-14 closed cell foam
Windows are foamed
Spray foam trailer
Gene checking wall temperature before foam spraying begins
Adddition was heated before closed cell foam was installed
Windows are protected from foam spray
Caulked corners and bottom plates
Attic baffles
Attic baffles
Trim and siding material are protected
One unit for fan and light
Framed chase in master closet
Powder room fan is installed
Powder room soffit
Hallway art arched niches
New beam in closet to hold upper floor
Shower seat and knee wall
Coffer ceilings are framed
New closet and hall walls are framed
Sierra Pacific windows are installed
Door is set in polyurethane sealant
Plumbing vents are in place
Shower valve and diverter are installed
New wall over frames existing
Transition of new and old floor
Roof covered with synthetic underlayment
Plywood barrier to protect existing space
Plastic barrier for dust control
Demolition of interior spaces to be remodeled
New bolted ledger to hold trusses
Trusses are installed, braced and sheathed
Vycor installed prior to window installation
View from southeast of framed addition
Wide cricket outlet
Double cricket is framed
Roof vents are cut
New roofs above adition
View from south of framed addition
Porch beams are bolted in pockets
Existing window is removed
Framed interior walls
Framed interior walls
Truss hangers are nailed
Truss girder is installed
Headers are open for insulation
Braced porch beam
Sheathed south walls
Sheathed west walls
Sheathed north walls
First walls
We frame open corners if possible
Plates for exterior walls
Exterior walls are installed on top of foam
New concrete curb around crawlspace access
New LVL header over crawlspace access
Joists are braced before sheathing
LSL rim is used
Parallel rim is reinforced with blocks
Foundation steps down
Carlos mixed concrete to block old window
Floor joists are installed
Sill plates are installed over spray foam
TimberStrand sill plates
Old window will be blocked with concrete wall
Granite countertop on new cabinets in TV room
Granite countertop installed
Prepping floor for vinyl flooring
Granite seat in new shower
Granite top installed in bathroom
Installing stone of face of bar
Placing concrete in forms
Placing concrete in forms
Pumping concrete over the house
Concrete placed in pump
Concrete pump to place concrete in walls
Forms prior to concrete placement
Forms prior to concrete placement
New caisson
Drilling caissons for addition
Drilling caissons for addition
Foundation excavation
Foundation excavation
Beginning foundation excavation
Sprinkler system valve box to be relocated
Trench at rear of lot
Trench for lateral relocate
Durock for bath walls
Basement bath floor protected
Floor is protected before drywall
Window at kids' area
Low voltage wiring
Framed floor above sump pit
Blocking in bar area
Blocking for TV mount
Cold air return is protected from dust
Registers are protected from dust
Mastic applied to ducts for better air flow
New breaker panel in mechanical room
Can lights above bar
Electricians installed boxes
Relocated water heaters
Dropped ceiling under ducts
Cold air return for basement
New ducts
A second furnace is installed
Chase was created for addition to sewer line
Ducts for future addition
Plumbing wall
Shower valve is installed
Shower pan is installed
Hallway and box column
Kids' area has little loft
Special area for kids
Can lights are installed
Steel column wrapped with PVC
Electric boxes in bar area
Plumbing for bar
Demolition of upper bathroom
Bricks were cut with grinder
Bricks removed for addition
Sewer & water connections for addition
Gravel protected for concrete mixing
Before new concrete placement
Added steel reinforcement for new concrete
Pex connections
New water lines
New underground plumbing
Framed soffits above bar
Soffit framing with gas line above
Framed soffits in TV room
Old stair wall is removed to open up view to basement
Gravel at bottom of new window well
A tree was removed
New finished window well
New window well is bolted to foundation wall
Carlos preparing to replace window well
Concrete slab pieces are moved out
Fence is removed and stored
Fence, rocks, & footings are removed
Rocks and dirt are kept separated
New window well is delivered
Silt fence is in place for erosion control
Silt fence around addition site for erosion control
Heat registers are taped
Plastic Zip door at stair landing
Future crawlspace access
Dust is ventilated out of basement
Blocks for dropped soffits are in place
This wall had to be hung on concrete anchors
Top plates are nailed and screwed
A box was built to protect the pool table
Studs are extra toenailed
Framed wall with plastic protection barrier in place
Framed basement walls double plated with void, per soils report
Closet has 45 degree walls
Concrete slab is removed for new plumbing
Concrete slab is removed
Exposed caisson for post adjustment
Concrete slab is cut
Concrete slab is cut for new plumbing
Plastic protection barriers installed before concrete cutting work
Bottom plates are glued and nailed
Framing material stored in basement to protect it
Wall lines are marked on floor
Plastic barrier to protect storage room